Mels, Kanton Sant Galen













Difficult working conditions due to rainy and windy weather, causing the paint to run, splatter or fail to dry properly.
Protection of work areas with plastic sheeting on scaffolding, securing surfaces against rain and wind, followed by cleaning and touch-ups of paint splashes once dry.
The façade of a new building covering 1,000 m² was scheduled to be painted within a few days. However, persistent rain and strong winds extended the project to almost two weeks. The challenging weather conditions required immediate solutions, additional protective measures, and extensive touch-ups and final corrections to ensure a clean, high-quality finish.